−1.7pts/yrReal growth per year, 2013–2023, vs. Jersey0.8%Unemployment18.9%Relative poverty, 202216.9%Lonely often or all the time, 20230Net new affordable homes, 20253.4 yearsInsurance Fund reserve, years of spending, 2026 budget6.4 yearsCare Fund reserve, years of spending, 2026 budget+64.3%Core-government pay bill, 2015 to 2025+34.2%Pay per public-sector post, 2015 to 20242,215Recorded offences, 202586%Chief Officer working days in the Bailiwick, 202557%Elective surgery on-target158Avoidable deaths per 100,000, 2022–2437.4Attainment 8, States-maintained schools, 202617 of 20Schools rated good or better for quality of education1,255Road closures, 2025140,860Bus journeys, March 2025+198%Electricity standing charge since July 202326.01p/kWhDomestic electricity unit rate, July 202639.5%FOI requests answered within 20 working days, 202563.6%FOI requests answered within 20 working days, 2026 so far

State of the NationGuernsey · Transport · 2021–2026

Road closures & the works programme.

Four Freedom of Information responses, cross-checked against a 13,466-row Trafficworx activity log - Guernsey publishes none of this as a standing dataset, so this is pulled together here for the first time.

Closure and signing costs, 2025
£270kClosure and signing costs, 2025
Road closures, 2025
1,255Road closures, 2025
Of all Trafficworx activity is a full road closure
46%Of all Trafficworx activity is a full road closure
Most road closures, 2,171 since 2021
St Peter PortMost road closures, 2,171 since 2021

Annual cost of road closures, 2021–2025

Traffic & Highway Services’ own cost of temporary closure implementation, traffic management and temporary signs (circa figures, as at 24 February 2026). It excludes signing for events, which applicants pay for, and temporary lights and barriers, which the contractor on site normally provides. 2025 also carried roughly £300k in admin and staffing costs, including utility-works coordination, which is not in this figure and was not given for earlier years (exception 2.9, disproportionate staff time). Trafficworx permits issued (all types) ran 2021: 2,304, 2022: 2,424, 2023: 2,887, 2024: 2,781, 2025: 2,725. Of 2,798 permits issued in 2025, 1,252 required an actual road closure.

From the raw log

Road closures by year

Derived directly from the raw Trafficworx activity-log export (13,466 rows, c. April 2020 to 23 July 2026), filtered to closure-type activities only - a different count basis to the FOI cost summary above, not directly comparable to it.

Complete yearPartial year (data to 23 Jul 2026)

2020 had only 2 rows in the log (data collection effectively starts 2021) and is omitted. 2026’s lighter bar (see legend) is a partial year - the export stops on 23 July 2026 - and should not be read as a down-year against 2024/2025. States of Guernsey FOI response, "Road Closure Data" (7 Aug 2026), including the TWXActivities270726 Trafficworx activity-log export; TWXActivities270726 - raw Trafficworx activity-log spreadsheet (13,466 rows, c. April 2020 to 23 July 2026)

Not every permit closes a road

Traffic management by type

All years combined (2021 to 23 July 2026). A road closure is the single largest category, but well under two-thirds of all Trafficworx activity.

“Other” buckets a small remainder (~7 rows) across One Way Cars, Contra-Flow and Diversion categories. States of Guernsey FOI response, "Road Closure Data" (7 Aug 2026), including the TWXActivities270726 Trafficworx activity-log export

Where and when

Road closures, year by year

Every logged road closure since 2021, plotted where it happened and coloured by the type of work behind it. Scrub or play through the years; the ranked parish totals alongside give the same data at a glance.

551 of 6,248 road closures aren’t shown - their logged road name couldn’t be matched to a mapped location.

Same data, ranked

  1. St Peter Port2,171
  2. Castel833
  3. Vale725
  4. St Martin664
  5. St Sampson562
  6. St Saviour333
  7. St Pierre du Bois311
  8. St Andrew306
  9. Forest199
  10. Torteval147

Pins are placed at the matched OpenStreetMap road location, not an exact worksite - for roads with multiple closures in the same year, zoom in to split a cluster apart. States of Guernsey FOI response, "Road Closure Data" (7 Aug 2026), including the TWXActivities270726 Trafficworx activity-log export; Parish administrative boundaries: OpenStreetMap contributors, ODbL

Bus service

Bus passenger numbers, above pre-COVID levels

The first quarter of 2025 was the highest on record for bus journeys, and March 2025 ran ahead of pre-COVID March 2019 - with passenger numbers up 34% across the last 12 years.

Total bus journeys January-March 2025 reached 382,262 - the highest on record for that quarter, even before the pandemic. Over the last 12 years, Guernsey bus passenger numbers rose 34%, per the Committee’s answer. Only two comparable monthly figures exist in that answer - not a monthly series. The question cites BBC reporting of a 47% increase over 12 years on the Jersey contract "due to subsidies" - which appears to describe subsidy cost rather than passenger numbers, and is not a like-for-like comparator for Guernsey's 34% passenger growth.

Reply by the President of the Committee for the Environment & Infrastructure to questions asked pursuant to Rule 14 of the Rules of Procedure by Deputy J. Gollop (ref. 2025-10, received 25 April 2025, replied 12 May 2025).

Air and sea links

Passengers leaving the island

Departing passengers by mode, comparing 2024 against 2023 and the last pre-COVID year, 2019 — the two benchmarks the States' own report uses, since 2020–2022 were COVID-distorted.

519,028 departing passengers, 2024

-8% on 2023, -25% on 2019 (pre-COVID). Excludes travel between the Bailiwick’s own islands.

63% by aeroplane

133,651 travelled by ferry (26%), the only mode to grow since 2023. Cruise ship passengers fell 67% against 2019, the steepest drop of any mode.

Departing passengers by mode

  1. Aeroplane327,603-21% vs 2019
  2. Ferry133,651-9% vs 2019
  3. Yacht19,318+16% vs 2019
  4. Cruise ship38,456-67% vs 2019

COVID-19 travel requirements were in force from Feb 2020, with no non-essential travel allowed 12 Mar-20 May 2020 or 14 Jan-22 Mar 2021, lifted entirely on 17 Feb 2022 - so the report itself compares 2024 against 2019 and 2022, not the intervening years. Yacht passenger counts before Q1 2023 were estimated from vessel numbers rather than counted directly, so the yacht row’s change figures carry more uncertainty than the other three modes. States of Guernsey Data & Analysis, "Guernsey Travel and Visitor Annual Report 2024" (issued 11 Feb 2025), Table 2.1.1

Infrastructure

Telecoms mast approvals

How many mobile phone mast planning applications have been approved in Guernsey since 2020, and by which operator - derived from a Freedom of Information response listing every application individually.

Mast approvals by year, 2020–2025

13 approved applications in total - but not 13 distinct masts: one of 2023’s six is a variation to an approval granted earlier the same year at the same site, so these cover 12 distinct proposals, several of them replacements of existing masts rather than new sites. 2025 covers only the period to 28 March 2025, the date of the FOI response - not a full year.

By operator

  • Sure Guernsey11
  • JT Guernsey2

“Sure Guernsey Ltd” and “Sure Guernsey Limited” are merged here as the same operator, as named variously in the source.

Freedom of Information response regarding telecommunications development (request received 26 March 2025, responded 28 March 2025), Planning Service.

Budget 2027

Transport in the 2027 Budget

Published 6 October 2026. Guernsey Ports returns a small deficit and Aurigny carries a £5.7m impairment; fuel duty and vehicle registration rise with inflation only.

Fuel duty: inflation only

Fuel duty and Vehicle First Registration Duty rise in line with inflation only, a deliberate pause after several real-terms rises.

Guernsey Ports: £332k deficit

Budgeted deficit of £332k in 2027 after a £319k forecast surplus for 2026, against a £2,051k actual loss in 2025. The States agreed to clear the Ports overdraft at the end of 2023 and continues to review the Island’s commercial port infrastructure.

Aurigny: £5.7m impairment

Aurigny continues to make a loss; the full £5.7m 2027 impairment for incorporated trading entities is Aurigny. The States’ Trading Supervisory Board is working on a long-term funding plan, and in the meantime Policy & Resources is topping up the airline’s liquidity to keep flights running.

Named 2027 transport capital projects

Four of the five itemised 2027 capital projects in Appendix VI are transport. They come out of a £29m Table 5 cyclical uplift intended to bring capital spend up to 2% of GDP. The report does not publish a project-by-project delay reconciliation, so slippage against earlier Budgets cannot be read off the page.

  • PFOS contaminated-soil removal, Airport£9.92m
  • QEII Gate, Harbours£0.75m
  • Bailiwick Air Navigation Systems£0.21m
  • Airport roof£0.15m
  • Combined, named transport capital 2027£11.04m

PFOS contaminated soil at the Airport is the largest named project in the whole 2027 capital pipeline. Appendix VI, pp.132–141.

See our full analysis of the 2027 Budget →

Storyboard

What Guernsey said

Four years of public comment on local politics, in eleven events

Open the storyboard

Stay up to date

New figures, as soon as the States publish them.

Join the group and we will post each update to this page, with what changed and where it came from.

Join the Facebook groupPublic group · free · no advertising