State of the NationGuernsey · Transport · 2021–2026
Road closures & the works programme.
Four Freedom of Information responses, cross-checked against a 13,466-row Trafficworx activity log - Guernsey publishes none of this as a standing dataset, so this is pulled together here for the first time.
- Closure and signing costs, 2025
- £270kClosure and signing costs, 2025
- Road closures, 2025
- 1,255Road closures, 2025
- Of all Trafficworx activity is a full road closure
- 46%Of all Trafficworx activity is a full road closure
- Most road closures, 2,171 since 2021
- St Peter PortMost road closures, 2,171 since 2021
Annual cost of road closures, 2021–2025
Traffic & Highway Services’ own cost of temporary closure implementation, traffic management and temporary signs (circa figures, as at 24 February 2026). It excludes signing for events, which applicants pay for, and temporary lights and barriers, which the contractor on site normally provides. 2025 also carried roughly £300k in admin and staffing costs, including utility-works coordination, which is not in this figure and was not given for earlier years (exception 2.9, disproportionate staff time). Trafficworx permits issued (all types) ran 2021: 2,304, 2022: 2,424, 2023: 2,887, 2024: 2,781, 2025: 2,725. Of 2,798 permits issued in 2025, 1,252 required an actual road closure.
States of Guernsey FOI response, "Costs of Road Closures for the Last 5 years" (19 March 2026); Guernsey Press, Andy Brown, "More than £500,000 spent last year on closing roads for repairs" (30 Mar 2026)
From the raw log
Road closures by year
Derived directly from the raw Trafficworx activity-log export (13,466 rows, c. April 2020 to 23 July 2026), filtered to closure-type activities only - a different count basis to the FOI cost summary above, not directly comparable to it.
2020 had only 2 rows in the log (data collection effectively starts 2021) and is omitted. 2026’s lighter bar (see legend) is a partial year - the export stops on 23 July 2026 - and should not be read as a down-year against 2024/2025. States of Guernsey FOI response, "Road Closure Data" (7 Aug 2026), including the TWXActivities270726 Trafficworx activity-log export; TWXActivities270726 - raw Trafficworx activity-log spreadsheet (13,466 rows, c. April 2020 to 23 July 2026)
Not every permit closes a road
Traffic management by type
All years combined (2021 to 23 July 2026). A road closure is the single largest category, but well under two-thirds of all Trafficworx activity.
“Other” buckets a small remainder (~7 rows) across One Way Cars, Contra-Flow and Diversion categories. States of Guernsey FOI response, "Road Closure Data" (7 Aug 2026), including the TWXActivities270726 Trafficworx activity-log export
Where and when
Road closures, year by year
Every logged road closure since 2021, plotted where it happened and coloured by the type of work behind it. Scrub or play through the years; the ranked parish totals alongside give the same data at a glance.
551 of 6,248 road closures aren’t shown - their logged road name couldn’t be matched to a mapped location.
Same data, ranked
- St Peter Port2,171
- Castel833
- Vale725
- St Martin664
- St Sampson562
- St Saviour333
- St Pierre du Bois311
- St Andrew306
- Forest199
- Torteval147
Pins are placed at the matched OpenStreetMap road location, not an exact worksite - for roads with multiple closures in the same year, zoom in to split a cluster apart. States of Guernsey FOI response, "Road Closure Data" (7 Aug 2026), including the TWXActivities270726 Trafficworx activity-log export; Parish administrative boundaries: OpenStreetMap contributors, ODbL
Bus service
Bus passenger numbers, above pre-COVID levels
The first quarter of 2025 was the highest on record for bus journeys, and March 2025 ran ahead of pre-COVID March 2019 - with passenger numbers up 34% across the last 12 years.
Total bus journeys January-March 2025 reached 382,262 - the highest on record for that quarter, even before the pandemic. Over the last 12 years, Guernsey bus passenger numbers rose 34%, per the Committee’s answer. Only two comparable monthly figures exist in that answer - not a monthly series. The question cites BBC reporting of a 47% increase over 12 years on the Jersey contract "due to subsidies" - which appears to describe subsidy cost rather than passenger numbers, and is not a like-for-like comparator for Guernsey's 34% passenger growth.
Air and sea links
Passengers leaving the island
Departing passengers by mode, comparing 2024 against 2023 and the last pre-COVID year, 2019 — the two benchmarks the States' own report uses, since 2020–2022 were COVID-distorted.
519,028 departing passengers, 2024
-8% on 2023, -25% on 2019 (pre-COVID). Excludes travel between the Bailiwick’s own islands.
63% by aeroplane
133,651 travelled by ferry (26%), the only mode to grow since 2023. Cruise ship passengers fell 67% against 2019, the steepest drop of any mode.
Departing passengers by mode
- Aeroplane327,603-21% vs 2019
- Ferry133,651-9% vs 2019
- Yacht19,318+16% vs 2019
- Cruise ship38,456-67% vs 2019
COVID-19 travel requirements were in force from Feb 2020, with no non-essential travel allowed 12 Mar-20 May 2020 or 14 Jan-22 Mar 2021, lifted entirely on 17 Feb 2022 - so the report itself compares 2024 against 2019 and 2022, not the intervening years. Yacht passenger counts before Q1 2023 were estimated from vessel numbers rather than counted directly, so the yacht row’s change figures carry more uncertainty than the other three modes. States of Guernsey Data & Analysis, "Guernsey Travel and Visitor Annual Report 2024" (issued 11 Feb 2025), Table 2.1.1
Infrastructure
Telecoms mast approvals
How many mobile phone mast planning applications have been approved in Guernsey since 2020, and by which operator - derived from a Freedom of Information response listing every application individually.
Mast approvals by year, 2020–2025
13 approved applications in total - but not 13 distinct masts: one of 2023’s six is a variation to an approval granted earlier the same year at the same site, so these cover 12 distinct proposals, several of them replacements of existing masts rather than new sites. 2025 covers only the period to 28 March 2025, the date of the FOI response - not a full year.
By operator
- Sure Guernsey11
- JT Guernsey2
“Sure Guernsey Ltd” and “Sure Guernsey Limited” are merged here as the same operator, as named variously in the source.
Budget 2027
Transport in the 2027 Budget
Published 6 October 2026. Guernsey Ports returns a small deficit and Aurigny carries a £5.7m impairment; fuel duty and vehicle registration rise with inflation only.
Fuel duty: inflation only
Fuel duty and Vehicle First Registration Duty rise in line with inflation only, a deliberate pause after several real-terms rises.
Guernsey Ports: £332k deficit
Budgeted deficit of £332k in 2027 after a £319k forecast surplus for 2026, against a £2,051k actual loss in 2025. The States agreed to clear the Ports overdraft at the end of 2023 and continues to review the Island’s commercial port infrastructure.
Aurigny: £5.7m impairment
Aurigny continues to make a loss; the full £5.7m 2027 impairment for incorporated trading entities is Aurigny. The States’ Trading Supervisory Board is working on a long-term funding plan, and in the meantime Policy & Resources is topping up the airline’s liquidity to keep flights running.
Named 2027 transport capital projects
Four of the five itemised 2027 capital projects in Appendix VI are transport. They come out of a £29m Table 5 cyclical uplift intended to bring capital spend up to 2% of GDP. The report does not publish a project-by-project delay reconciliation, so slippage against earlier Budgets cannot be read off the page.
- PFOS contaminated-soil removal, Airport£9.92m
- QEII Gate, Harbours£0.75m
- Bailiwick Air Navigation Systems£0.21m
- Airport roof£0.15m
- Combined, named transport capital 2027£11.04m
PFOS contaminated soil at the Airport is the largest named project in the whole 2027 capital pipeline. Appendix VI, pp.132–141.